IN THE HIGH COURT FOR THE STATE OF TELANGANA
AT HYDERABAD
WEDNESDAY, THE THIRTEENTH DAY OF NOVEMBER
TWO THOUSAND AND NINETEEN
PRESENT
THE HONOURABLE SRI JUSTICE A.RAJASHEKER REDDY
Arbitration Application No. 6 of 2014
Between:
M/s. R.K. Infra and Engineering (India) Pvt. Ltd, Having registered office
at 7-2-49/75, Nizampet Road, Hyder Nagar, Hyderabad 500 072
Represented By its Managing Director Mr. B. Ravi Kalyan Reddy.
...Petitioner.
AND
M/s. RATNA Infrastructure Projects Pvt. Ltd., Plot No.88, Prasasan Nagar,
Roacl No.72, Jubilee Hills, Hyderabad-33, Represented by its Chairman anc-l
Managing Director.
...Respondent
Application Under Sec. 16 of the Arbitration & Conciliation Act, 1996
praying that in the circumstances stated in the affidavit filed therewith, the
High Court may be pleased to appoint an arbitrator for adjudication of
the disputes between the parties.
Counsel for the Petitioner: Sri B.Chandrasen Reddv.
Counsel for the Respondent: Sri S.U.V.Srinivas.
The Court made the following: ORDER
THE }!!)N BLE SRI JUSTICE A.RAJASHEKER RE=DIY
ARIIII RA ON APPLICATION NO.5 0F 4
This Arbitration Application is filed under Sectic,n :1"1 (6) of the
Arbitration and (lorciliation Act, 1996 (for short'the A:t cf 1996'), read
with Rule-2(b) of the Scheme for Appointment of Arbitrators, 1996, for
appointment of an Arbitrator for adjudicating and settlement of the dispute
by passing an auiarrj,
2. It is the case of the applicant that it is a compan) re,3istered under
the provisions c,f the Companies Act, 1956; that it is errgaged in the
business of prosper:ting, exploring, operating, excavatiol, (:onstruction of
roads, earth works, etc in India; that Meja Ufia Nigam Pvt Ltd (hereinafter
referred to as "M[JNPL") has awarded the work of ";ite levelling and
infrastructure urork, package for its project Meja Thermal Po\^/er Project" to
the respondent. and a contract agreement dated 21.9..:010 was entered
into between MUNPL and the respondent; that the resporrdent entered into
a deed of lvlemorandum of Understanding dated 18.11.2019 with
M/s Rithwik Projects Pvt Ltd, Hyderabad, to ward the wlrole of the above-
mentioned work on 100o/o back to back basis subject to the terms and
conditions agreed thereunder; that the said M/s Rithwik Prrtjects Pvt Ltd,
Hyderabad, an,l the applicant have entered into a Joint Vr:nture namely
Rithwik-RK Infra Joint Venture on 28.7.2010 for executon of the above-
mentioned work subject to the terms and conditions arlreed thereunder;
that the respondent has subcontracted the whole work cn 100o/o back to
back basis on Fl.ithr,r,ik-RK Infra Joint venture and entered intc sub-contract
agreement on 28.7.2010; that condition No.13 of the agreement
ORDER:
7
empowered the respondent to issue power of attorney in the name of the
representative of loint Venture Company for the purpose of dealing with
the MUNPL with respect to the execution of work; that M/s Rithwik entered
into an agreement under a Memorandum of Understanding on 29,7.2010
with the applicant to execute the entire work on sub-contract basis on
behalf of the Joint venture subject to the terms and conditions agreed
thereon; that pursuant to the above agreements and understanding
between the parties, the applicant had deployed entire machinery and men
at site as per the contract and was executing the entire work contract; that
leaving a balance of Rs.74,20,9t,7391-; that however, the parties to the
Joint venture have terminated the joint venture agreement by executing
the Dissolution Deed dated 28.7.2012 and desired to execute the
remaining work worth Rs.74,20,91,739l- individually holding equal shares;
that the respondent subcontracted the work per the ratio decided to the
applicant and M/s Rithwlk at Rs.37,10,45,869/- each and entered into
separate subcontract agreements with the respective parties on 28.7.2012;
that M/s Rithwik has subcontracted their share of 500/o work to the
applicant as per the modified agreement dated 28.7.2012; that the
applicant was executing the balance works under the said contracu and
that out of the total contract value of Rs.137,2L,75,3271-,lhe value of the
work executed by the applicant as on the above date worked out to
Rs.90,98,34,857/-.
3. It is the further case of the applicant that as an amount of
Rs.27,28,26,000/- was not released by MUNPL, the applicant issued legal
the value of work executed by the Joint Venture Company worked out to
Rs.63,00,83,588/- as against the total contract value of Rs.t37,2L,75,3271-
notice dated -..4.7)..2013 for invoking the arbitration tlau:;e in the Sub-
contract agreement, dated 28.7.20t2 and dentanding to pay
Rs.29,63,76,755/-. The respondent has issued reply to the sald notice on
30.11.2013 disputirg the liability apart from raising othr:r contentions and
also stated that before going for arbitration, the dispute: has to be settled
amicably and then': is no arbitrary dispute for referrin,; to arbitrator. As
such, the present A,rbitration Application is filed.
4. Heard learned counsel for the applicant and learned :ounsel for the
respondent. Nr: counter affidavit is flled on behalf of the resl)ondent.
5. Learned coursel for the applicant while reiteratirrg the contents in
the Arbitration Application submits that when there is dispute regarding
payment of arrount by the respondent to the appliclnt, the applicant
issued notice to the respondent seeking to invoke the arbitration clause;
and that in the reoly, the respondent has only disputerd the liability. He
further submits that though the applicant was agreeabk: for amicable
settlement, the respondent has not come forward for the same and that
therefore, having no other go, the present Arbitration Application is filed.
6. There is no dlspute with regard to existence of ai bitration clause in
the Sub-contract agreement dated 28.7.2012 entered intr: between the
parties, the invocation of arbitration under clause 14 therer.rnder and also
with regard to issuance of notice by the applicant and th,: reply sent by the
respondent thereto. Exchange of notices regarding payrren: goes to show
that there exists dispute.
7. In this c,ase, it is to be seen that the Sub-contracl agreement dated
28.7.2012 contains arbitration clause, which reads as unrler:
"lf an'r' dispute or difference of any kind whatsoeve r shall arise
behveen PATNA and Rithwik-RK (JV) in connecton with or
1
arising out of this agreement or the carrying out of the
Services whether arising durlng the progress of the Works or
after their completion, an attempt to amicably settle the same
shall be made between the authorized representatives of
RATNA and Rithwik-RK (lV), failing which such disputes shall
be flnally, immediately settled by arbitration in accordance
with the provisions of the Arbitration and Conciliation Act,
1996, and/or any re-enactment and amendments thereof. The
parties herein also agree to constitute a three panel arbitrator
proceedings, either party shall appoint, one arbitrator each
and the appointed two arbitrators shall appoint the third
arbitrator in accordance with the provisions of the Arbitration
Act. The venue of the arbitration proceedings shall be at
Hyderabad, and the language shall be English."
8. In view of the same, Sri Justice Amitava Roy, Former Judge of the
Supreme Court of India, is appolnted as Arbitrator to adjudicate the claims
and disputes between the parties and to pass an award in accordance with
law.
9. The learned Arbitrator shall be entitled to fees as per the rates
specified in the Fourth Schedule to the Act of 1996, inserted by Act 3 of
2016 with effect from 23.10.2015, which shall be borne by both partles in
equal proportion.
10. The Arbitration Application is accordingly allowed.
11. Interlocutory applicatlons pending, if any, shall stand closed. No
order as to costs.
Sd/-M.SANTHI VARDHANI
JOINT REGIS AR
//TRUECOPY//
SECTIO FFICER
To,
1. Sri Justice Amitava Roy, Former Judge of the Supreme Court of India,
A-96,2"a Floor, Defence Colony, New Delhi-110024.
2. One CC to Sri B.Chandrasen Reddy, Advocate [OPUC]
3. One CC to Sri S.U.V.Srinivas, Advocate [OPUC]
4. Two CD Copies
IR\
4-
TIIGH COURT
ARR,J
DATED:13l11,/2011)
ORDER
ARBAPPL.No.6 o12014
Allowing the Arbitration Application.
o
-rHE SIa
(
)
0? ,tUr 2020J
(.
),
.,,4;:ilpAT(:H
a
3sv
6 c-otrruj
)- r\r\.,-
i\
.i/
|